Create a dated record for each audit, named accessibility-audit-record-<date>.md, and retain it with the release evidence. Publish only public-safe information required by the accessibility statement.

Copy this file. Fill every cell. Do not delete a section. A blank cell is a result nobody recorded, so write Not tested instead.

Results​

Every result cell holds one of these four words.

ResultMeaning
PassSomeone ran the check in every environment the row names and found nothing.
FailThe check found a barrier. Link the issue or the change that fixed it.
Not testedNobody ran the check. Give the reason. It counts against a conformance claim.
Not applicableThe surface has no such content or step. Explain why.

Not tested and Not applicable are different answers. The first says the evidence is missing. The second says there is nothing to gather. If the tester, assistive technology, or test data was missing, record a check that could not run as Not tested.

When a result differs between environments, or ran in only some of them, name the environment in the cell, for example Fail (E2) or Pass (E1).

Audit​

FieldValue
Dates
Revision and release
Scope and sample rationale
Deployment and test data
Evaluator
WCAG-EM report
Storybook report, revision and browser
Finding query

Environments​

Give each environment an ID (E1, E2, …) and list what was run in it. An environment that was planned and not run stays in the table as Not tested.

IDOperating systemBrowserAssistive technologyVersions and relevant settingsRun

Findings​

One row per failure, with the issue or change that fixes it and the story or test that fails without the fix.

FindingSurfaceCriterionBarrierFix or issueCoverage

Surfaces​

Automated is the axe run, plus the title, reflow and motion checks. Keyboard is a Tab walk of the surface: order, focus indicator, focus not hidden and no trap. Link each failure to its issue.

SurfaceRoute, state and roleAutomatedKeyboardNVDAVoiceOverEvidence or issue

Complete processes​

One row for each process in each environment. A process is complete when a person finishes it from the first step to the last, including the error they make on the way.

ProcessRoles and statesEnvironmentSuccess pathError recoveryEvidence or issue

Remaining work​

List each Not tested result and what a tester has to run to close it.